This happens on a lot of sites, and it’s rarely an accident. It’s how most payment schedules are written.
Why schedules are front-loaded
A contractor needs cash to start: mobilisation, labour advances, the first lots of steel and cement. That part is fair. But many schedules go further: a large advance, then big payments at each slab, until most of the money is gone by the time the structure is up.
The structure is the fast, visible part of the job. Finishing is slower, fiddlier, and where quality is won or lost. If the money has already gone, so has your leverage.
This isn’t dishonesty. It’s how contractors protect their own cash flow. But your schedule should protect yours.
The principle: every payment follows verified work
A good schedule has four features:
- A modest advance, enough to mobilise, not enough to finance the job.
- Stage payments tied to work you can check, not to dates or to how long it’s been.
- Payments in proportion to the value of each stage, so you’re never far ahead of the work.
- A retention: a portion held back until handover and the defects period, so snags actually get fixed.
Stages, and what to check before you pay
| Stage | Check before you release payment |
|---|---|
| Mobilisation advance | Contract signed, scope and BOQ agreed, site set up |
| Excavation and foundation | Depth and footing sizes as per drawings, steel checked before concrete |
| Plinth and damp-proof course | DPC laid properly before walls go up |
| Each slab | Shuttering, steel size, spacing and cover checked before the pour |
| Brickwork and lintels | Walls in line and plumb, lintels over every opening |
| Roof waterproofing and slope | Water test: water must run to the drains |
| Electrical and plumbing first fix | Wire sizes, conduits and pipes checked before plaster covers them |
| Plaster | Even surface, corners straight, curing done |
| Finishing | Snag list agreed and worked through |
| Handover | Final account signed; retention held for the defects period |
The most important column is the second one. Several of these checks can only happen once: after the pour, the plaster or the tiles, the evidence is gone.
If you’re building from abroad
Distance makes front-loading worse. A photo of a wall tells you a wall exists, not what’s inside it. Before each payment, ask for:
- a video walk-through with a measuring tape in shot
- photos of the steel before the pour, with a scale reference
- a short written note of what was done, against the BOQ
Better still, have someone independent check the stage before you pay. It costs far less than paying for work that isn’t there.
When the schedule is already signed
If you’ve already agreed a front-loaded schedule, you can still protect yourself:
- Track the value of work done against what you’ve paid, every month.
- Hold any discretionary payments until each stage is verified.
- Renegotiate the remaining payments around stages before finishing starts. That’s where your remaining leverage matters most.
The hard part
The rule is simple. Following it is hard. The contractor says the labour won’t come without payment. The family says, “Don’t upset him, the work will stop.” Holding a payment until a stage is checked feels rude. It isn’t. It’s what the contract is for.
Questions owners ask
How much advance should I pay a contractor?
Enough to mobilise the site, and no more. The rest should follow verified stages.
What is retention money?
A portion of each payment held back until handover and the end of the defects period, so there’s a reason for snags to get fixed.
Should I pay by date or by stage?
By stage. Dates reward time passing; stages reward work done.
Can I change a payment schedule after signing?
Only by agreement, but most contractors will discuss restructuring the remaining payments, especially before finishing starts.